PULSEKITA · STALLED PROJECTS · CASE STUDY

Sabah Pan Borneo: Delayed Packages, Not an Abandoned Highway

The audit recorded four of 35 packages completed by March 2026; that is not the physical-progress percentage.

SabahStaged highway project affected by delaysLast sourced status: 2026-10-19
Pan Borneo WP19 construction sign in Silam, Sabah in 2025; not representative of the whole highway.
WP19 construction sign in Silam, 20 June 2025. Credit: Taufik / Wikimedia Commons, CC0 1.0; unmodified original. Only one work package, not all of Phase 1. Original photo and creator ↗ · Reuse licence (CC0-1.0) ↗

Sabah's Pan Borneo Highway is a multi-package programme with different starting dates and progress levels. Calling the entire highway abandoned would mislead readers.

Project category

Staged highway project affected by delays

Last documented status

Four packages completed by March; PAC announced a follow-up inquiry on 19 October 2026 while other packages remained under way

Latest source date used

Editorial review

— not a live site inspection

TIMELINE · SOURCE-DATED EVENTS

How did it happen?

  1. The original implementation agreement began, according to reporting on the audit.

  2. The original Phase 1 completion target was reported; timelines subsequently changed.

  3. LKAN 2/2026 recorded four of 35 packages completed and 31 still under implementation.

  4. The Works Ministry addressed the audit and distinguished completed package counts from phase-level physical progress.

  5. The Public Accounts Committee announced an inquiry into delays and delivery issues highlighted by the audit.

Four of 35 does not mean 11.4% overall progress

Four completed packages represent 11.4% of the package count. In the ministry's October response, physical progress as of 25 August was reported as 89.01% for Phase 1A, 37.58% for WP09 and 23.96% for Phase 1B. Those metrics have different scopes and dates.

Of the packages still underway as of 31 March 2026, the audit identified nine as troubled, 13 behind schedule and nine ahead of schedule. That is not a declaration that the whole highway is abandoned.

Why did schedules slip?

The Works Ministry cited delivery-model changes, the pandemic, land acquisition, utility relocation and contractor performance as delay factors. The audit also identified planning and monitoring weaknesses.

A photo of one work package or construction sign cannot represent the entire route. Historical images must identify their location and capture date.

OPEN QUESTIONS

What still needs to be checked?

  • Which packages were actually completed and handed over after the audit?
  • What are the latest phase-by-phase progress measures and schedules?

EVIDENCE AND SOURCES

Sources behind this account

These are the public records and reports consulted for this article. Status may change after their publication dates; newer official documents should be checked before reaching a fresh conclusion.

  1. Bernama — Pan Borneo Highway: KKR To Address Audit Findings ↗Source date: 2026-10-08
  2. Sabah Media — Empat daripada 35 pakej siap setakat Mac 2026 ↗Source date: 2026-10-06
  3. Malaysiakini — PAC siasat kelewatan projek Pan Borneo Sabah ↗Source date: 2026-10-19

Read the other cases

Jalan Pudu, Kuala Lumpur1996

Plaza Rakyat: Three Decades of Unfinished Concrete in Kuala Lumpur

From an integrated transport-hub ambition to a long-running dispute over land and revival.

Read →
Ulu Gombak, Selangor1994

Mimaland: The Theme Park Reclaimed by Forest

Once a family destination famous for dinosaur displays, now a case study in the fragility of leisure destinations.

Read →
Hulu Selangor, Selangor2025

Lembah Beringin: Unfinished Homes and a Community Waiting

Beyond the 'ghost town' label are buyers, residents and an unresolved search for rescue developers.

Read →
Melaka City, Melaka2010

Melaka Monorail: The Tourist Line That Stopped Running

The RM16.5 million tourist attraction that sparked a familiar question: revive it or retire it?

Read →
Putrajaya2004

Putrajaya Monorail: Two Decades Without a Train

Unused bridge and tunnel structures show why a transport proposal cannot simply be restarted.

Read →
Beaufort, Sabah2017

Kampung Selagon PPR: Completed Homes Still Unoccupied

The 2026 audit recorded 67 unoccupied units and stalled remedial works.

Read →
Langkawi, Kedah2024

Galeria Perdana: Terminated Upgrade and Rising Completion Estimate

The Langkawi museum upgrade faced contract termination and a revised RM56.4 million completion estimate.

Read →
Jalan Tun Razak, Kuala Lumpur2017

From M101 Skywheel to KL360: 337 Buyers and a Revival Plan

A stalled development has been relaunched under a new name, but its 2030 completion is still a target.

Read →
Subang Jaya, Selangor2012

Empire Remix 1: A Revival Plan After More Than 13 Years

HCK announced its involvement in reviving the project now called Subang Sentral; completion is not yet verified.

Read →