Sabah's Pan Borneo Highway is a multi-package programme with different starting dates and progress levels. Calling the entire highway abandoned would mislead readers.
Staged highway project affected by delays
Four packages completed by March; PAC announced a follow-up inquiry on 19 October 2026 while other packages remained under way
— not a live site inspection
TIMELINE · SOURCE-DATED EVENTS
How did it happen?
The original implementation agreement began, according to reporting on the audit.
The original Phase 1 completion target was reported; timelines subsequently changed.
LKAN 2/2026 recorded four of 35 packages completed and 31 still under implementation.
The Works Ministry addressed the audit and distinguished completed package counts from phase-level physical progress.
The Public Accounts Committee announced an inquiry into delays and delivery issues highlighted by the audit.
Four of 35 does not mean 11.4% overall progress
Four completed packages represent 11.4% of the package count. In the ministry's October response, physical progress as of 25 August was reported as 89.01% for Phase 1A, 37.58% for WP09 and 23.96% for Phase 1B. Those metrics have different scopes and dates.
Of the packages still underway as of 31 March 2026, the audit identified nine as troubled, 13 behind schedule and nine ahead of schedule. That is not a declaration that the whole highway is abandoned.
Why did schedules slip?
The Works Ministry cited delivery-model changes, the pandemic, land acquisition, utility relocation and contractor performance as delay factors. The audit also identified planning and monitoring weaknesses.
A photo of one work package or construction sign cannot represent the entire route. Historical images must identify their location and capture date.
OPEN QUESTIONS
What still needs to be checked?
- Which packages were actually completed and handed over after the audit?
- What are the latest phase-by-phase progress measures and schedules?
EVIDENCE AND SOURCES
Sources behind this account
These are the public records and reports consulted for this article. Status may change after their publication dates; newer official documents should be checked before reaching a fresh conclusion.
- Bernama — Pan Borneo Highway: KKR To Address Audit Findings ↗Source date: 2026-10-08
- Sabah Media — Empat daripada 35 pakej siap setakat Mac 2026 ↗Source date: 2026-10-06
- Malaysiakini — PAC siasat kelewatan projek Pan Borneo Sabah ↗Source date: 2026-10-19