From M101 Skywheel to KL360: 337 Buyers and a Revival Plan

A stalled development has been relaunched under a new name, but its 2030 completion is still a target.

Jalan Tun Razak, Kuala LumpurMixed-use development under revivalLast sourced status: 2026-06-06
Fictional AI observation wheel in Kuala Lumpur; NOT the actual KL360 design or evidence of completion.
Fictional observation-wheel concept. NOT a photograph, approved design, or evidence that KL360 has been built or completed. The 2030 date remains a target. AI-GENERATED CONCEPT — fictional imagery, not a photograph of the project or actual site. Depicted buildings, surroundings and construction progress are unverified. Do not treat this image as evidence of site conditions.

Behind the new branding is the central question of whether existing purchasers are protected and construction will actually be completed.

Project category

Mixed-use development under revival

Last documented status

Revival announced June 2026; completion targeted for 2030, not yet delivered

Latest source date used

Editorial review

— not a live site inspection

TIMELINE · SOURCE-DATED EVENTS

How did it happen?

  1. M101 Skywheel was launched before work later stalled.

  2. A revival scheme supported by a majority of buyers was endorsed by the High Court, according to Bernama.

  3. The project was relaunched as KL360 @ Menara GD; the housing minister referred to 337 affected purchasers.

  4. The developer's full completion target is 2030 and remains to be verified when reached.

What changed under the revival?

Bernama reported the KL360 @ Menara GD relaunch with a RM1.37 billion gross development value. GDV is not equivalent to public spending, rescue costs or compensation to buyers.

The 337 affected purchasers were associated with sale and purchase agreements worth more than RM306 million. Revival is meaningful progress, but not a handover of completed homes.

What needs monitoring?

Physical construction progress, safety certification, the delivery timetable for original purchasers and transparent contract changes are stronger indicators than launch ceremonies.

This article follows the position reported in June 2026 and does not assume subsequent construction milestones.

OPEN QUESTIONS

What still needs to be checked?

  • Are verified construction milestones and original buyer handover dates being published?
  • What protections exist in the court-endorsed revival scheme?

EVIDENCE AND SOURCES

Sources behind this account

These are the public records and reports consulted for this article. Status may change after their publication dates; newer official documents should be checked before reaching a fresh conclusion.

  1. Bernama — KL360 @ Menara GD Reborn, Promises Sky-high Living and New Hope ↗Source date: 2026-06-06
  2. Bernama — KPKT Revives 1,576 Sick And Abandoned Housing Projects Since 2023 ↗Source date: 2026-06-06

Read the other cases

Jalan Pudu, Kuala Lumpur1996

Plaza Rakyat: Three Decades of Unfinished Concrete in Kuala Lumpur

From an integrated transport-hub ambition to a long-running dispute over land and revival.

Read →
Ulu Gombak, Selangor1994

Mimaland: The Theme Park Reclaimed by Forest

Once a family destination famous for dinosaur displays, now a case study in the fragility of leisure destinations.

Read →
Hulu Selangor, Selangor2025

Lembah Beringin: Unfinished Homes and a Community Waiting

Beyond the 'ghost town' label are buyers, residents and an unresolved search for rescue developers.

Read →
Melaka City, Melaka2010

Melaka Monorail: The Tourist Line That Stopped Running

The RM16.5 million tourist attraction that sparked a familiar question: revive it or retire it?

Read →
Putrajaya2004

Putrajaya Monorail: Two Decades Without a Train

Unused bridge and tunnel structures show why a transport proposal cannot simply be restarted.

Read →
Beaufort, Sabah2017

Kampung Selagon PPR: Completed Homes Still Unoccupied

The 2026 audit recorded 67 unoccupied units and stalled remedial works.

Read →
Langkawi, Kedah2024

Galeria Perdana: Terminated Upgrade and Rising Completion Estimate

The Langkawi museum upgrade faced contract termination and a revised RM56.4 million completion estimate.

Read →
Sabah2016

Sabah Pan Borneo: Delayed Packages, Not an Abandoned Highway

The audit recorded four of 35 packages completed by March 2026; that is not the physical-progress percentage.

Read →
Subang Jaya, Selangor2012

Empire Remix 1: A Revival Plan After More Than 13 Years

HCK announced its involvement in reviving the project now called Subang Sentral; completion is not yet verified.

Read →