Behind the new branding is the central question of whether existing purchasers are protected and construction will actually be completed.
Mixed-use development under revival
Revival announced June 2026; completion targeted for 2030, not yet delivered
— not a live site inspection
TIMELINE · SOURCE-DATED EVENTS
How did it happen?
M101 Skywheel was launched before work later stalled.
A revival scheme supported by a majority of buyers was endorsed by the High Court, according to Bernama.
The project was relaunched as KL360 @ Menara GD; the housing minister referred to 337 affected purchasers.
The developer's full completion target is 2030 and remains to be verified when reached.
What changed under the revival?
Bernama reported the KL360 @ Menara GD relaunch with a RM1.37 billion gross development value. GDV is not equivalent to public spending, rescue costs or compensation to buyers.
The 337 affected purchasers were associated with sale and purchase agreements worth more than RM306 million. Revival is meaningful progress, but not a handover of completed homes.
What needs monitoring?
Physical construction progress, safety certification, the delivery timetable for original purchasers and transparent contract changes are stronger indicators than launch ceremonies.
This article follows the position reported in June 2026 and does not assume subsequent construction milestones.
OPEN QUESTIONS
What still needs to be checked?
- Are verified construction milestones and original buyer handover dates being published?
- What protections exist in the court-endorsed revival scheme?
EVIDENCE AND SOURCES
Sources behind this account
These are the public records and reports consulted for this article. Status may change after their publication dates; newer official documents should be checked before reaching a fresh conclusion.
- Bernama — KL360 @ Menara GD Reborn, Promises Sky-high Living and New Hope ↗Source date: 2026-06-06
- Bernama — KPKT Revives 1,576 Sick And Abandoned Housing Projects Since 2023 ↗Source date: 2026-06-06