PULSEKITA · STALLED PROJECTS · CASE STUDY

Kampung Selagon PPR: Completed Homes Still Unoccupied

The 2026 audit recorded 67 unoccupied units and stalled remedial works.

Beaufort, SabahCompleted public housing affected by structural damageLast sourced status: 2026-10-05
Generic AI concept of Malaysian housing; NOT Kampung Selagon PPR and not evidence that its 67 units are occupied.
Generic AI-generated housing scene. NOT Kampung Selagon PPR; does not depict documented damage or actual occupancy. AI-GENERATED CONCEPT — fictional imagery, not a photograph of the project or actual site. Depicted buildings, surroundings and construction progress are unverified. Do not treat this image as evidence of site conditions.

A house can be reported as completed without being fit for occupation. Kampung Selagon illustrates why construction status and ground conditions must be assessed together.

Project category

Completed public housing affected by structural damage

Last documented status

All 67 units remained unoccupied as of July 2026 according to LKAN 2/2026

Latest source date used

Editorial review

— not a live site inspection

TIMELINE · SOURCE-DATED EVENTS

How did it happen?

  1. The RM23.70 million PPR project was completed, according to audit findings published in 2026.

  2. A RM2.72 million contract to rebuild eight units and repair five was mutually terminated at 15% progress.

  3. The audit found 67 units unoccupied and 13 seriously damaged by ground movement.

  4. Findings from LKAN 2/2026 were reported publicly, including failed remediation.

What does 'completed' mean here?

The Auditor-General distinguished completion of the original works in 2017 from habitability. Ground movement caused structural damage, preventing occupation of the completed units.

The figure of 13 refers to severely damaged units, not the total number of empty homes. All 67 were reported unoccupied as of July 2026.

Why did remediation stall?

The RM2.72 million remedial contract ended on 11 March 2025 at 15% physical progress. That percentage refers to the later repair contract, not the original PPR construction.

This article does not claim handover after July 2026. An updated safety assessment and repair timetable are needed before changing the stated status.

OPEN QUESTIONS

What still needs to be checked?

  • What ground stabilisation and building safety measures are planned?
  • When can any habitable units be handed over?

EVIDENCE AND SOURCES

Sources behind this account

These are the public records and reports consulted for this article. Status may change after their publication dates; newer official documents should be checked before reaching a fresh conclusion.

  1. Bernama — Six 12th Malaysia Plan Development Projects Face Implementation Issues ↗Source date: 2026-10-05
  2. FMT/Bernama — 6 projek pembangunan RMK12 berdepan masalah pelaksanaan ↗Source date: 2026-10-05

Read the other cases

Jalan Pudu, Kuala Lumpur1996

Plaza Rakyat: Three Decades of Unfinished Concrete in Kuala Lumpur

From an integrated transport-hub ambition to a long-running dispute over land and revival.

Read →
Ulu Gombak, Selangor1994

Mimaland: The Theme Park Reclaimed by Forest

Once a family destination famous for dinosaur displays, now a case study in the fragility of leisure destinations.

Read →
Hulu Selangor, Selangor2025

Lembah Beringin: Unfinished Homes and a Community Waiting

Beyond the 'ghost town' label are buyers, residents and an unresolved search for rescue developers.

Read →
Melaka City, Melaka2010

Melaka Monorail: The Tourist Line That Stopped Running

The RM16.5 million tourist attraction that sparked a familiar question: revive it or retire it?

Read →
Putrajaya2004

Putrajaya Monorail: Two Decades Without a Train

Unused bridge and tunnel structures show why a transport proposal cannot simply be restarted.

Read →
Langkawi, Kedah2024

Galeria Perdana: Terminated Upgrade and Rising Completion Estimate

The Langkawi museum upgrade faced contract termination and a revised RM56.4 million completion estimate.

Read →
Jalan Tun Razak, Kuala Lumpur2017

From M101 Skywheel to KL360: 337 Buyers and a Revival Plan

A stalled development has been relaunched under a new name, but its 2030 completion is still a target.

Read →
Sabah2016

Sabah Pan Borneo: Delayed Packages, Not an Abandoned Highway

The audit recorded four of 35 packages completed by March 2026; that is not the physical-progress percentage.

Read →
Subang Jaya, Selangor2012

Empire Remix 1: A Revival Plan After More Than 13 Years

HCK announced its involvement in reviving the project now called Subang Sentral; completion is not yet verified.

Read →