Galeria Perdana is an existing museum, not a never-opened building. The audit concerns its upgrade works; it must not be misread as declaring the whole museum abandoned.
Disrupted museum upgrade project
Upgrade contract terminated; completion tender expected in February 2027 per October 2026 audit
— not a live site inspection
TIMELINE · SOURCE-DATED EVENTS
How did it happen?
The RM20.4 million upgrade contract was terminated after four extensions totalling 192 days.
The project was handed to the Public Works Department for follow-up.
The audit reported that estimated completion cost had risen by RM36 million to RM56.4 million.
The audit anticipated a completion-contractor tender; this is a projection, not confirmation that it occurred.
Reading the costs correctly
RM20.4 million was the terminated upgrade contract value. RM56.4 million was an estimated completion figure in the audit, not evidence that the entire sum has been spent.
The audit also referred to contractual delay damages. Different financial figures describe different concepts and should not be combined into an unsupported loss estimate.
What comes next?
A new tender was expected in February 2027 according to the report published in October 2026. An actual completion date requires updated procurement or contract evidence.
An archival photo of Galeria Perdana depicts the premises only when photographed, not the condition of the upgrade works during the audit.
OPEN QUESTIONS
What still needs to be checked?
- Will the new tender proceed on schedule?
- What final budget and completion schedule will be approved?
EVIDENCE AND SOURCES
Sources behind this account
These are the public records and reports consulted for this article. Status may change after their publication dates; newer official documents should be checked before reaching a fresh conclusion.
- FMT/Bernama — Six 12MP projects faced implementation issues ↗Source date: 2026-10-05
- FMT/Bernama — 6 projek pembangunan RMK12 berdepan masalah pelaksanaan ↗Source date: 2026-10-05