Sabah Pan Borneo: how did a 2021 completion target become 2030?

An accountability chronology of Phase 1—from its 2015 plan and original 2021 completion window through the PDP model change, repeated target shifts and the Auditor-General's 2026 findings.

Year by year11 peristiwa2015-01-01 → 2026-10-05
RINGKASAN KRONOLOGI BERGERAKLihat urutan peristiwa sebelum membaca cerita penuh.
2015-01-01→2026-10-05
CERITA SEPINTAS LALU

Lihat urutan peristiwa sebelum membaca cerita penuh.

An accountability chronology of Phase 1—from its 2015 plan and original 2021 completion window through the PDP model change, repeated target shifts and the Auditor-General's 2026 findings.

11 PERISTIWA14 PAUTAN SUMBER
PERISTIWA 1 DARIPADA 112015Phase 1 is planned as a 706 km, 35-package highway programme.

The Works Ministry later told Parliament that the preliminary 2015 construction estimate was RM12.86 billion. The Auditor-General says the project was planned from 2015.

WHERE THINGS STAND NOWThe highway is still under construction, with the overall Phase 1 target now extending to 2030.

The latest audit is based on project status as at 31 March 2026, while later Works Ministry statements set a phased package-completion path through 2030. The immediate question is how the government responds to the audit findings while keeping that revised schedule credible.

Teruskan ke kronologi penuh ↓
GARIS MASA PENUH · SKROL / KLIK / GERAK UNTUK TEROKAI
Cara membaca kronologi PulseKita

Setiap langkah mempunyai tarikh dan sumber. Kenyataan, dakwaan, keputusan dan tindakan yang disahkan dipisahkan supaya kronologi tidak menukar dakwaan sesuatu pihak menjadi fakta.

BAGAIMANA KITA SAMPAI KE SINI

Ikuti urutan, bukan tajuk sahaja.

03
22 September 2019KEPUTUSAN

Project management moves from the PDP model to the Works Ministry.

The government terminated the Project Delivery Partner model and continued Phase 1 using a conventional federal contracting approach, with the Works Ministry taking over implementation.

The Works Ministry later said the model change followed a 2019 government decision. This is a delivery-model change, not by itself proof that one party caused all subsequent delays.

05
16 May 2023STATUS

Two packages are complete; the remaining active packages are targeted for end-2024.

Sabah's Works Minister said progress across 15 active Phase 1 packages had reached 79.06%, with two packages completed and the rest then targeted for completion by the end of 2024.

Package counts and phase groupings changed as the programme was restructured, so PulseKita keeps each progress figure tied to the reporting basis used at that time.

07
21 April 2025STATUS

Four Phase 1A packages are complete; Phase 1B is still at an early stage.

Works Minister Alexander Nanta Linggi said four of 16 Phase 1A packages were complete, Phase 1A progress was 81.7%, and all 19 Phase 1B packages were under implementation at 3.06% progress.

08
13 May 2026STATUS

The government publishes a package-by-package path stretching to 2030.

Deputy Works Minister Ahmad Maslan said nine more packages were expected to complete in 2026, four in 2027, 12 in 2028, three in 2029 and the final three by 2030.

09
14 July 2026WANG

Parliament hears that the current Phase 1 allocation is RM24.889 billion.

The Works Ministry contrasted the current RM24.889 billion total for Phase 1A and 1B with the preliminary RM12.86 billion estimate from 2015.

The ministry stressed that the 2015 figure was a preliminary construction estimate under the original PDP model, so PulseKita does not present the difference as a simple cost overrun calculation.

11
5 October 2026AMARAN

The Auditor-General puts the decade-long delivery problems under a fresh spotlight.

Using a 31 March 2026 snapshot, LKAN 2/2026 says only four of 35 work packages were complete; of 31 still under implementation, nine were classified as sick projects, 13 were behind schedule and nine were ahead.

The audit also identified RM513.99 million in variation orders approved beyond authorised limits, plus planning, utility-relocation, monitoring and contract-governance weaknesses.

WHERE THINGS STAND NOW

The highway is still under construction, with the overall Phase 1 target now extending to 2030.

The latest audit is based on project status as at 31 March 2026, while later Works Ministry statements set a phased package-completion path through 2030. The immediate question is how the government responds to the audit findings while keeping that revised schedule credible.

KONGSI URUTAN INIKonteks lebih berguna apabila dikongsi bersama.

Kongsi kronologi penuh yang mempunyai sumber, bukan tangkap layar tanpa konteks.

APA YANG MASIH BELUM TERJAWAB

Soalan yang kronologi ini masih belum dapat jawab.

01How many additional packages have actually reached full completion since the Auditor-General's 31 March 2026 snapshot?

02What corrective action will be taken over the RM513.99 million in variation orders that the audit says exceeded authorised approval limits?

03Will additional funding be required beyond current allocations to complete all 35 packages?

04Can the nine packages classified as sick projects recover without moving the 2030 target again?

05What will the final delivered cost of Phase 1 be once all packages and outstanding claims are closed?

APA YANG PERLU DIPANTAU SETERUSNYA

Peristiwa yang boleh mengubah perkembangan cerita ini.

01A formal Works Ministry or JKR Sabah response to LKAN 2/2026.

02Completion/opening of the packages scheduled for 2026.

03Recovery plans for sick and delayed work packages.

04Any supplementary allocation or revised cost ceiling.

05Any revision to the Q4 2030 overall completion target.